Broadmoor Street Construction
 
Posted on Wednesday November 27, 2019
 
Road construction: Check here for updates on the Broadmoor Street road construction project between Johnson Drive and Martway Street.
 
Last Updated: November 27, 2019 Broadmoor Completed PavementThe project south of Johnson Drive is nearly complete. The traffic signal is expected be delivered in December, it was delayed due to a manufacturing defect. The bases for the signal have been poured. Crews are expected to pave Broadmoor Street north of Johnson Drive the week of December 2. There will be traffic impacts but those will be minimized as much as possible. Please use extra caution in the area and obey all traffic signs.
Project Details The project includes full-depth street reconstruction between Johnson Drive and Martway, stormwater upgrades, new street lighting, improved sidewalk connectivity, and reduced lane width for an improved pedestrian experience. A new traffic signal installed at the Johnson Drive and Broadmoor intersection, and the intersection will be treated with mill and overlay.
Completed Work
Sod is being placed Sidewalk and retaining wall concrete work is nearly complete at the southwest corner of Johnson Drive and Broadmoor. Traffic striping on Broadmoor south of Johnson Drive Asphalt has been placed on the road bed south of Johnson Drive Bases of street lights and the traffic signal have been set. Installation of street light bases. Pouring sidewalks and curb on the east and west sides of Broadmoor. Laying first two layers of asphalt on the east side of the street. Demolition of concrete and pavement on the eastern side of the project. Installation of stormwater infrastructure on eastern side of the project.
Utility relocations have been completed. - Johnson County Wastewater has completed their work in the area. - AT&T has completed repair to manhole covers in the Johnson Drive intersection. - Kansas Gas has completed relocations of their utility lines in the area. - WaterOne has completed replacing the water line in Broadmoor Street between Martway and Johnson Drive.
 
City of Mission
6090 Woodson    Mission, KS 66202    |    City Hall: 913-676-8350    |    Community Center: 913-722-8200    |   Emergency: 911
Site Map   |  Contact Us   |   Powered by MunicipalCMS
 
E-notify RSS Feeds Twitter Facebook 
0